Greenspace logo
Welcome
Climate
  • Home
  • Policy & Reporting
  • Bulletin Board
  • Legal Register
    • Full Report
    • Calendar
    • Monthly Updates
    • Help
  • Docs
  • Policy & Reporting
  • Bulletin Board
  • ยป
    Legal Register
    • Full Report
    • Calendar
    • Monthly Updates
    • Help
  • Docs

Client Login

Legal Register - Climate

Environmental
  • Select Month:
    • April 2025
    • March 2025
    • February 2025
    • January 2025
    • December 2024
    • November 2024
    • October 2024
    • September 2024
    • August 2024
    • July 2024
    • June 2024
    • May 2024
    • April 2024
    • March 2024
    • February 2024
    • January 2024
    • December 2023
    • November 2023
    • October 2023
    • September 2023
    • August 2023
    • July 2023
    • June 2023
    • May 2023
    • April 2023
    • March 2023
    • February 2023
    • January 2023
    • December 2022
    • November 2022
    • October 2022
    • September 2022
    • August 2022
    • July 2022
    • June 2022
    • May 2022
    • April 2022
    • March 2022
    • February 2022
    • January 2022
    • December 2021
    • November 2021
    • October 2021
    • September 2021
    • August 2021
    • July 2021
    • June 2021
    • May 2021
    • April 2021
    • March 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • August 2020
    • July 2020
    • June 2020
    • May 2020
    • April 2020
    • March 2020
    • February 2020
    • January 2020
    • December 2019
    • November 2019
    • October 2019
    • September 2019
    • August 2019
    • July 2019
    • June 2019
    • May 2019
    • April 2019
    • March 2019
    • February 2019
    • January 2019
    • December 2018
    • November 2018
    • October 2018
    • September 2018
    • August 2018
    • July 2018
    • June 2018
    • May 2018
    • April 2018
    • March 2018
    • February 2018
    • January 2018
    • December 2017
    • November 2017
    • October 2017
    • September 2017
    • August 2017
    • July 2017
    • June 2017
    • May 2017
    • April 2017
    • March 2017
    • February 2017
    • January 2017
    • December 2016
    • November 2016
    • October 2016
    • September 2016
    • August 2016
    • July 2016
    • June 2016
    • May 2016
    • April 2016
    • March 2016
    • February 2016
    • January 2016
    • December 2015
    • November 2015
    • October 2015
    • September 2015
    • August 2015
    • July 2015
    • June 2015
    • May 2015
    • April 2015
    • March 2015
    • February 2015
    • January 2015
    • December 2014
    • November 2014
    • October 2014
    • September 2014
    • August 2014
    • July 2014
    • June 2014
    • May 2014
    • April 2014
    • March 2014
    • February 2014
    • January 2014
    • December 2013
    • November 2013
    • October 2013
    • September 2013
    • August 2013
    • July 2013
    • June 2013
Preview Email
March 2021
Congratulations. There are no changes to the legislation or other requirements in your legal register.
 
Recent Publications

New publications this month:

HEALTH AND SAFETY EXECUTIVE (HSE)

Keeping workplaces safe as coronavirus (COVID-19) restrictions are eased – sources of advice

Guidance has been published reflecting the relaxation of COVID-19 restrictions.

 

Talking with your workers about preventing coronavirus (COVID-19)

This guidance has been updated.

 

Biocide Article 95 Suppliers – approaching deadline

The HSE has published an eBulletin on biocides. This reflects that to remain on the GB Article 95 list of biocides after 31 December 2022, companies must:

  • resubmit the active substance dossier / data or letter of access to HSE; and
  • confirm the company is established in the UK

Suppliers can complete both actions at the same time or independently, however both actions must be completed by 31 December 2022. The full original EU application must be submitted, alongside any data gathered or generated since the original submission.

 

Biocides: Applications for product authorisation and active substance approval

This eBulletin concerns the Biocidal Products regime in Great Britain. Applications for GB product authorisation (including renewals) and active substance approval (including renewals) need to be resubmitted to HSE by the deadlines stated.

 

Submitting chemicals information to the National Poisons Information Service

This eBulletin provides guidance on how chemical companies should submit information to the National Poisons Information Service under the retained Classification, Labelling and Packaging (CLP) Regulation. Different arrangements apply in Great Britain and Northern Ireland, due to the Northern Ireland protocol.

 

 

SCOTTISH GOVERNMENT

Practical fire safety - existing high rise domestic buildings: guidance

Guidance on the management of fire safety in existing high risk domestic buildings was updated during March 2021.

 

 

HEALTH AND SAFETY EXECUTIVE NORTHERN IRELAND (HSENI)

Enforcement guidelines for health and safety at work in Northern Ireland

This guidance sets out general principles and the approach to be taken when the HSENI undertakes enforcement decisions.

 
Offences

Construction companies fined following failure of working platform

Two companies have been sentenced following an incident were a working platform failed and a worker using the platform was injured.

On 1 July 2019, Dere Street Homes Limited was acting as principal contractor. The company had provided components for a proprietary polypropylene working platform at a new build in Wheatley Hill, County Durham. SGS Construction & Design Limited were acting as a contractor and supplied workers to erect the working platform.

The working platform failed and a bricklayer using the platform was injured.

An HSE investigation found that a number of components were missing from the working platform. Although workers previously supplied by SGS were formally trained in the erection of the components to form a safe working platform, the worker who erected the failed platform had not received adequate training.

The working platform had earlier been signed off by a site manager working for Dere Street Homes. When this manager left, a number of months prior to the incident, the inspection and signing off of the working platform was no longer undertaken.

Breaches

Dere Street Homes Limited pleaded guilty to  breaching Regulation 13(1) of the Construction (Design & Management) Regulations 2015.

  • Regulation 13(1) requires principal contractors to plan, manage and monitor the construction phase and coordinate health and safety matters to ensure, so far as is reasonably practicable, construction work is undertaken without risk to health or safety.

SGS Construction & Design Limited pleaded guilty to breaching Regulation 15(2) of the Construction (Design & Management) Regulations 2015.

  • Regulation 15(2) requires that contractors plan, manage and monitor construction work carried out either by the contractor or by workers under the contractor’s control to ensure that, so far as is reasonably practicable, it is carried out without risks to health and safety.

Penalties

Dere Street Homes Limited was fined £38,000 and ordered to pay costs of £5,367.30.

SGS Construction & Design Limited was fined £8,000 and ordered to pay costs of £2,683.60.

 

Garage fined after mechanic suffers life-changing injuries in a fall

A garage has been fined after an employee suffered life changing injuries when he fell into a vehicle inspection pit.

On 3 September 2018, an employee of GP Motors Works Ltd on the Isle of Wight fell into a vehicle inspection pit more than five feet deep whilst carrying out mechanical repairs to a nearby vehicle.

The vehicle inspection pit was partially covered with a small vehicle, leaving around seven feet of the pit uncovered and without any other measures to prevent exposing employees to an unnecessary fall risk. The employee sustained serious head and shoulder injuries, which required surgery.

An HSE investigation found the company had failed to ensure the pit had any physical measures, such as barriers or pit covers, in place to prevent a person falling into it.

Breach

GP Motor Works Ltd pleaded guilty to breaching Section 2(1) of the Health and Safety at Work Act 1974.

  • Section 2(1) requires employers to ensure, so far as is reasonably practicable, the health, safety and welfare at work of their employees.

Penalty

GP Motor Works Ltd was fined £10,000 and ordered to pay costs of £10,000.

 

Fines after Shropshire foundry was found to have exposed workers to hand-arm vibration risks

Saint-Gobain Construction Products UK Limited, who operate a large foundry in Telford, has been fined after a number of its workers were diagnosed with hand arm vibration syndrome (HAVS).

Newcastle-under-Lyme Magistrates’ Court heard how three employees, the earliest of which had used vibrating tools at the company since 1989, had developed and were subsequently diagnosed with HAVS in 2016.

Despite the diagnosis, one of the workers continued working with vibrating tools without effective control measure. The employees used tools such as hand grinders, air chisels, spindle grinders, and earlier in their employment, jackhammers, to finish cast iron drainage products.

An HSE investigation found that until 19 December 2017, the company’s vibration risk assessment did not identify each employee’s daily exposure to vibration and did not measure cumulative exposures of using different vibrating tools throughout a shift.

The HSE investigation also found there was inadequate health surveillance in place and employees were not made aware of HAVS and its symptoms. Despite health surveillance notifying the company of a HAVS diagnosis, the company had failed to take effective action to adjust the affected worker’s job, meaning that staff continued to be exposed to excessive vibration.

Breach

Saint-Gobain Construction Products UK Limited pleaded guilty to failing to discharge the duties imposed upon it by Section 2(1) of the Health and Safety at Work Act 1974.

Penalty

Saint-Gobain Construction Products UK Limited was fined £500,000 and ordered to pay costs of £9,453.

Waterman Greenspace