Climate News Greenspace Demo - Climate Space Greenspace Climate Update: July 2015


Welcome to the Climate News Greenspace Demo - Climate Space Greenspace Climate Update: July 2015 monthly email as part of your subscription to Waterman's Greenspace platform. The monthly updates show any:

  • new legal entries added to your register;
  • amendments to legal entries in your register; and
  • legal entries removed from your legal register.

It also contains links to new publications from Government and regulatory bodies and examples of relevant offences, highlighting how legislation is implemented and enforced in practice.
As well as receiving this update by email you will also find it saved on your Greenspace site under the Legal Register > Monthly Updates tab at the top of your Greenspace page.


 
 
 
 
July 2015
 
 
Congratulations. There are no changes to the legislation or other requirements in your legal register.
 
 
 
 
 
 
 
 
Recent Publications
 
 

ENVIRONMENT AGENCY

Waste classification technical guidance WM3: Technical guidance on how to assess and classify waste

This document provides guidance on waste classification. This reference manual is aimed towards anyone involved in producing, managing and regulating waste.

 

Temporary water discharges from excavations: Environment Agency regulatory position statement for temporary dewatering excavations such as for construction activities

This guidance explains requirements on the discharge of uncontaminated water from excavations.

This document has been updated to reflect changes to legislation, non-native species risk and the archiving of PPG6.

 

Comply with the Energy Savings Opportunity Scheme (ESOS)

This guidance document has been updated for clarity purposes and to provide further information on UKAS accredited ISO 50001 certification bodies.

 

MCERTS: radio analytical testing of environmental and waste waters

This guidance sets out requirements on radioanalytical testing of environmental and waste waters in accordance with the MCERTS standard. This document has been revised to reflect monitoring requirements.

 

SCOTTISH GOVERNMENT

Shifting Normal: how to design projects that change things for the better

This guide is designed to help community groups tackling climate change maximise their success by taking account of how change happens when planning, carrying out and reviewing their activities.

 

WELSH GOVERNMENT

Towards zero waste: Wales’ overarching waste strategy document

Towards Zero Waste sets out a strategy of how waste in Wales will be managed to produce benefits for the environment, economy and social wellbeing.

 
 
 
 
 
 
 
Offences
 
 

Surrey waste site ordered to pay £19,000

A waste company in Worcester Park in Surrey has been ordered to pay a total of £19,000 in fines and costs after pleading guilty at Guildford Crown Court to operating an illegal waste transfer station.

The court heard how the site was being used to store 4,000 tonnes of construction and demolition waste, alongside at least 17 skips of builders’ waste. The company had previously been warned about taking waste.

The waste company was in breach of the Regulation 12 of the Environmental Permitting (England and Wales) Regulations 2010 as they were operating a waste facility without an environmental permit or exemption. This constitutes an offence under Regulation 38(1)(a).

The company was fined £10,000, ordered it to pay £9,000 towards the prosecution’s costs, and was ordered to pay a victim surcharge of £120.

 

Former waste operator fined £700 for breaching environmental licence

Former waste operator, John Burnett has been fined a total of £700 at Edinburgh Sheriff Court, after being found guilty of breaching the conditions of a Waste Management Licence .

SEPA officers conducting site inspections of Dalkeith Demolition’s site in Dalkeith while it was in operation between 2007 and 2011 rated the site as “poor” under the compliance assessment scheme. It was identified that waste was being stored on an area of the site which was not suitably surfaced. Following the identification of this issue, the officers granted a four moth period to remedy this. A subsequent inspection identified that this issue had not been resolved.

Further to the above issue, a site inspection on 24 August 2011 identified that the quantity of waste held exceeded the licensed limit of 1,000 tonnes and that was continued to be stored inappropriately.

Dalkeith Demolition went into voluntary liquidation in January 2012, when a large quantity of waste was left on the site.

John Burnett was sentenced for breaches of the Section 33(6) to the Environmental Protection Act 1990.

 

Penalties of £11,000 imposed on a Newry man for fuel laundering waste offences

Francis McGuinness of Newry, Northern Ireland was today found guilty and fined £5,000 at Newry Magistrates' court for a breach of waste management legislation. He was also order to pay £6,000 in clean-up costs, £255 to NIEA for analysis costs and a £25 offender levy.

During a site visit on 4 December 2013, NIEA, PSNI and HMRC officers identified that a large quantity of hazardous controlled waste from fuel laundering had been deposited on the site. No licence was held concerning this waste.

Mr McGuinness was found guilty on one charge under Article 4(1)(b) of the Waste and Contaminated Land (Northern Ireland) Order 1997, which prohibits the treatment, keeping or disposal of waste on land or by means of any mobile plant unless in accordance with a waste management licence.

 
 
 
 
 
 
Kenny Wintle
e: kenny.wintle@watermangroup.com

Waterman Infrastructure & Environment Ltd
2nd Floor | Cubo | 38 Carver Street | Sheffield | S1 4FS | t: 0114 2298900
Pickfords Wharf | Clink St | London | SE1 9DG, t: 0207 928 7888

Waterman Greenspace takes the burden out of your Management Systems and the hard work from Compliance.

Waterman has taken all reasonable precautions to ensure that information contained in this bulletin is accurate, but stresses that the content is not intended to be comprehensive. Waterman recommends that no action be taken on matters covered in this bulletin without taking full professional advice. Waterman holds the copyright for the Legal Update which is sent to you on the basis that it should not be used or reproduced in any material or other medium produced by you or passed to any third parties without the prior consent of Waterman.
 
 
 

 
 
 
 
 
 
 
 

 
 
 
© 2025 Waterman Group plc
 
 
 


The contents of this e-mail and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom it is addressed. Any views stated herein do not necessarily represent the view of the company and are those of the individual sender, except where it specifically states them to be the views of the Company.
No confidentiality or privilege is waived or lost by any mis-transmission. If you have received this e-mail in error please delete it and all copies and e-mail a notification to the sender. Any dissemination, distribution or copying of this e-mail is strictly prohibited and may constitute a breach of confidence.


All reasonable precautions have been taken to see that no viruses are present in this e-mail. Waterman Group cannot accept liability for loss, disruption or damage however caused, arising from the use of this e-mail or attachments and recommend that you subject these to virus checking procedures prior to use.
E-mail messages may be monitored and by replying to this message the recipient gives their consent to such monitoring.